The basement, ground floor and level 1 concrete pours have been completed, with structural works continuing to progress across the upper levels. Level 2 construction activities are underway, including ongoing formwork, reinforcement installation, services coordination, and preparation works ahead of upcoming pours. Structural elements such as walls, columns, and core works are progressing in line with the construction programme, maintaining steady momentum across the project.

Basement services installation has commenced, with inground services and building infrastructure works progressing alongside the structural programme. Ongoing coordination between structural, hydraulic, electrical, mechanical, and fire services is being undertaken to ensure efficient integration as construction advances.